YEAR COMPLETED:

Nov. 11, 2010

PROJECT DETAILS:

Trendsetter accomplished a  2 ½ -month schedule to design, build and test four umbilical termination assemblies complete with bases, junction plates, welded tubing, electrical, and hydraulic flying leads to meet all ExxonMobil GP specifications.  Normal delivery of this type of equipment is typically longer than 1 year.